Water harvesting, water treatment, preservation and expansion of traditional handloom and handicraft

 

 Water harvesting, water treatment

        Haflong is the only Hill station of Assam. Until recently a good number of Tourist have come here and there are more scope for further tourism development. Due to last ethnic clash between the Dimasas and Hmars the law and order problem of the District during 2003 was bad. This aspect has been lowered down to a considerable extent, now the law and order and social condition of this hill station has improved leaving scope for improvement of the tourism.

        For continuous investment of fund there has been perceptible development in the tourist spot but these development were not enough for achieving the optimum goal.

        Hence  to  fill   up  the  gaps   requirement  of more  funds  is   felt  necessary   under S D.A. through R.S.V.Y. in 3 years.

 IMPACT

The present programme of improvement of five lakes proposed to provide drinking water by improved treatment of the water, after removing the silt with this 40,000 thousand people of Haflong Town will be benefited by way of getting pure drinking water; more over since the present social system of N.C, Hills is peaceful on implementation of this project there will be more tourist. At least 5000 thousand tourist are expected in the next five years.

The year wise allocation of fund for three years are as follows :-    

 1st year    -       Rs.  28.10 Lakhs.

  2nd year  -       Rs.  85.15 Lakhs   

 3rd year    -       Rs.217.24 Lakhs

Total                  Rs.330.49 Lakhs

Since the programme is planned    to be completed within the 3 years and flow of fund is expected to be obtained within 2007.

A list of scheme with financial involvement (Rs. in lakhs) is given below.

1.Lower Lake at Haflong       -               Rs. 1,14,07,000.00

2. Bazar Lake at Haflong      -               Rs.    95,78,500.00

3. Kalibari Lake at Haflong   -               Rs.    40,14,400.00

4. Dibarai lake at Haflong                     Rs.,   55,83,700.00

5. Lake near Govt. Boys H.S.School                Rs.    14,65,400.00

6. Construction of retaining wall            Rs.    10,00,000.00

    at Boys H.S.School 

                                        Total         Rs. 3,30,49,000.00

 

( Rupees Three Crore Thirty  lakhs fortynine thousand) only.

         These five natural lakes is the major points of importance of tourist attractions as they provide not only the scope of maintaining ecological balance in this only hill station of Assam but also provide scope for aquatic sports. These lakes as have not been maintain properly for many years, due to siltation water become filthy and create un hygienic situation. On implementation of the project the work desiltration water purification, construction of boundary walls, retaining walls, beautification works will be taken up. On completion the water reservoir of the lakes will also provide drinking water facilities after proper purification which is still a problem area of the district.  

 PUBLIC HEALTH ENGINEERING

          N.C. Hills District having a population of 1,86,000 souls, is the habitation of several hilly ethnic tribes - very simple, colourful & economically backward. The problem of drinking water is a chronic problem as the existing infrastructure of this department is quite inadequate to meet up the growing demand of the urban as well as the rural areas.

The annual rainfall of this district is approximately 2000 mm. Hilly streams & rivers are the major source of water with an exception of underground strata at limited pockets. The inhabitants are mainly dependent on the streams & in all the habitations water is carried by gravity, pumping as required to meet up the demand. The water at the proposed villages thus are also to be collected from the surface source,

ON GOING SCHEMES

There are total 584 nos. of piped water supply schemes under different programmes. (Completed = 184 nos., Commissioned = 258 nos. & On going = 142 nos.). But majority of the on going schemes are not functioning properly due to inadequate infrastructural support. So is the scarcity & acute shortage. Hence new schemes are proposed with improved infrastructure and construction designee.

CONSTRAINTS & GAPS

The major constrains faced by the department for achieving the targets, is the paucity of fund. Due to acute financial crunch, the existing infrastructural features cannot be maintained up to the mark. While undertaking the new assignments, a small percentage of tasks can be executed in comparison to the pre-assumed targets.

Besides, the Govt. of India has already sanctioned 120 nos. piped water supply schemes under ARP for an estimated cost of Rs. 475.00 Lakhs. But work of these schemes could not be taken up due to less allocation of fund under ARP every year. Allocation under ARP amounting to Rs. 150.00 Lakhs is necessary every year for taking up the already sanctioned schemes under ARP.

 INTERVENTION

 

It is proposed to take up to

 

(1)    Provide drinking water facilities to 67000 souls in 3(three) years as per an annual allocation of Rs.96.03 Lakhs, Rs.186.05 Lakhs and Rs. 217.92 Lakhs and in total amount Rs. 500.00 Lakhs in 3(three) (i.e. 2005 to 2007) years.

 

(2)     1,17,400 nos. of mandays will be generated.

 

        (3)    25 nos. of villages will be benefited.

 

(4)                           The economy of the district will be improved considerably on indirect way and the standard of life of the people will be improved.

(5)    Water users associations will be formed against each proposed schemes for running and maintenance of the schemes and the water users association shall bear the cost of maintenance.

Year-wise and physical and financial target with schematic details are given herewith.

(6)    Drinking water users society would be formed for maintenance of the schemes.

YEAR-WISE PHYSICAL AND FINANCIAL TARGET

HAFLONG PHE DIVISION

Sl. No

Scheme

Estimated Cost

(Rs.in lakhs)

Year-wise plan outlay (in lakhs)

Physical target

(in %)

1st yr.

2nd yr.

3rd yr.

1st yr.

2nd yr.

3rd yr.

1.

Construction of Jatinga W/S/S

70.61

10.00

30.00

30.61

14.16

42.48

43.36

2.

Construction of Harangajao w/s/s

83.94

15.00

30.00

38.94

17.87

35.75

46.39

3.

Construction of Gunjung w/s/s

53.50

8.00

22.00

23.50

14.95

41.12

43.93

4.

Construction of Haflong Hindu w/s/s

10.78

1.50

3.50

5.78

9.27

21.65

69.08

5.

Construction of Boulmoul Pt-II w/s/s

5.14

1.00

2.00

2.14

19.45

38.90

41.65

6.

Construction of distribution network under Haflong w/s/s

70.00

20.00

20.00

30.00

28.00

29.00

43.00

7

Construction of Digtrik Water Supply Scheme

15.00

3.00

6.00

6.00

20.00

40.00

40.00

8.

Construction of Hadingma w/s/s

15.00

3.00

6.00

6.00

20.00

40.00

40.00

9.

Construction of Dehangi Bazar w/s/s

10.00

3.00

3.00

4.00

30.00

30.00

40.00

10.

Water testing kit @Rs.20000/

10.00

2.00

4.00

4.00

10 Nos.

20 Nos.

20 nos.

11.

Nobdilangting-Drangbra w/s/s

52.00

10.00

20.00

22.00

19.00

38.00

43.00

12.

Langting Greater w/s/s

45.00

8.00

17.00

20.00

16.00

38.00

46.00

13.

Borolongbong w/s/s

10.95

1.50

3.50

5.95

13.69

31.95

54.36

14.

Construction of D/N/W Umrangso w/s/s

38.03

7.61

15.21

15.21

20

40.00

40.00

15.

Construction Sangbar w/s/s

4.58

0.92

1.83

1.83

20

40.00

40.00

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

YEAR-WISE PHYSICAL AND FINANCIAL TARGET

HAFLONG PHE DIVISION

 

Sl. No.

Scheme

Estimated Cost

(Rs. in lakhs)

Year-wise plan outlay (in lakhs)

Physical target (in %)

1st yr.

2nd yr.

3rd yr.

1st yr.

2nd yr.

3rd yr.

16.

Construction of  D/N/W Boro Lokhingdong w/s/s

2.33

0.48

0.95

0.90

20

40

40

17.

Construction of  D/N/W Choto lokhingdong w/s/s

3.14

1.02

1.06

1.06

32

34

34

Total

500.00

96.03

186.05

217.92

 

 

 

       

 Preservation and expansion of handloom & handicraft of the tribal people.

                Weaving which has been the most widely practiced crafts in this hill district since the time beyond memory. Handloom and weaving plays an important role in the socio-economic life of the local people of the N.C. Hills. About 30%of the total textiles requirements of the district come from the handloom sector. Handloom assumes importance for the people of the district, because it is not only to meet the clothing needs of the people but give expressions to our art and culture, our craftsmanship and heritage. It has the high potential to provide self-employment for gainful occupation to the rural population with minimum investment.

In this district, out of the total population of l,86,189 as per 2001 census, 20,027 are the weavers as per 1995-96, handloom and power loom census, conducted by the Govt. of India. These weavers are under below the poverty line and they are found expert in weaving

         Under central sector and centrally sponsored scheme, following are the details of the ongoing projects:-

 

Sl. No.

Year of sanction.

Name of the scheme

Central Sector/ Centrally sponsored

Amount sanctioned and utilised

No. Of person benefited

Remarks

1

2

3

4  .

5

6

7

1

1997-98

P.P scheme at Rangapur

Centrally sponsored

4.95

50 Nos.

 

2

-do-

P.P. scheme at Langting

Centrally sponsored

4.95

50 Nos.

 

3

1998-99

P.P. scheme at Mahur

Centrally sponsored

5.10

50 Nos.

 

4

1998-99

P.P. scheme at Maibang

Centrally sponsored

5.10

50 Nos.

 

5

1998-99

P.P. scheme at Mahadev-Tilla

Centrally sponsored

5.10

50 Nos.

 

6

1998-99

P.P. scheme at Haflong

Centrally sponsored

5.10

50 Nos.

 

7

1998-99

P.P. scheme at Umrangso

Centrally sponsored

5.10

50 Nos.

 

8

1998-99

P.P. scheme at Dittock-Cherra

Centrally sponsored

5.10

50 Nos.

 

 

       CONSTRAINTS   :-   Although   there   has   been   considerable growth   and development  activities under the  control  of Autonomous  Council, N.C.  Hills optimum growth and development works of Handloom and Textiles could not be taken up for non-availability of sufficient fund. Till recently, we could provide assistance and pack-up support to 960 nos. of weavers leaving the major section of weavers as unprivileged.

          IMPACT:-    On implementation of the present project with  ‘the financial allocation of Rs.144.00 lakhs, within timely completion of the same is within 2007 following benefits will be achieved.

960 trained unemployed weavers will be rehabilitated in Handloom sector. Each weaver will be benefited as follows.

I.      (a) Fly shuttle frame loom complete with all accessories

—1 set @ Rs.6000= Rs. 6000.00

        (b) Yarn( as their working capital in kinds)  -------@ Rs.4800= Rs. 4500.00

        (c) G.C.I. sheet                                   --------@ Rs.4000= Rs. 4000.00

        (d) carrying charge and others               --------@ Rs.200  = Rs.   500.00

                                                                                Total = Rs.15,000.00

 (II)   (a) Construction expenditure including other materials like timber, bamboo, labour charges etc. for making workshed------------                                                                        -   @ Rs. 4500 = Rs. 4500.00

                ( to be borne by beneficiary)

 

                               Grand Total ( I+II)                        = Rs. 19,500.00

  These projects will ensure gainfully economic activities to Dautuhaja, Gunjung, Hadingma, Diyangmukh, Harangajao, Mupa, Thaijuwari, Kalachand, Maibang and Dehangi areas etc.

 Following are the details of the proposed programmes :-   (Rs. In lakh)

 

Name of scheme

Year wise Requirement

Total fund required

No. of beneficiaries to be benefited 

 

2004-05

2005-06

2006-07

2004-05 to 2006-07

RSVY

Individual/ Bank Finance

RSVY

Individual/ Bank Finance

RSVY

Individual/ Bank Finance

RSVY

Individual/ Bank Finance

Distribution of Fly shuttle loom with accessories to loom less weavers, yarn and GCI sheet for self employment under RSVY.

a) looms – 21.60

b) Yarn -16.20

c) GCI sheet

-14.40

d) Carrying charge 1.8

a) Construction of w/Shed

-16.20

a) looms 13.50

b) Yarn 10.125

c) GCI sheet

-9.00

d) Carrying charge 1.125

a) Construction of w/Shed

10.125

looms 22.50

b) Yarn 16.875

c) GCI sheet

-15.00

d) Carrying charge 1.875

a) Construction of w/Shed

16.875

looms 57.60

b) Yarn 43.20

c) GCI sheet

-38.40

d) Carrying charge 4.8

a) Construction of w/Shed

43.20

960 Nos.

(1st Year-360 no.

2nd year-225 No.

3rd year-375 no.)

 

Grand Total

54.00

16.20

33.75

10.125

56.25

16.875

144.00

43.20

960 Nos.

There will be 64 nos. of SHG consisting of 15 nos. of beneficiaries in each group. In the 1st year there will be 24 nos. group and thus cover 360 nos. of weavers, in the 2nd year there will be 15 nos. of group and thus cover 225 nos. of weaver. Lstly in the 3rd year there will be 25 nos. of groups and thus cover 375 nos. of weavers. Thus all total 960 nos. of weavers will be benefited.

        The cost of construction of worksheds @ 30% of the total schematic value would be borne by the beneficiary. As provision of ongoing CSS/SGSY, revolving fund @ 15000.00 per SHG will be provided and that will be adjusted from the fund proposed to be contributed by the groups for the sustainment of the project. From the proposed fund with addition of self contribution and bank finance of 25% of the total schematic value will be spent in infrastructure.

 

  Sericulture

        Sericulture is an age old cottage industry practiced mainly by the rural people. Sericulture in the district is being promoted by the Department of Sericulture headed by Addl. Director having two zones, Haflong and Maibang. People are still resorting to primitive takli method of Eri-spinning resulting in less production, poor quality yarn and less income. But Nos. of improved charkhas for Eri spinning are developed recently to overcome the disadvantages of takli method. One spinner now can produce about 350 grams of spun yarn per day on modern spinning charkha against that of only 80-100 grams on takli method. Altogether 90 Nos. of S.H.G.s would be formed and 900 nos. of beneficiaries would be benefitted.

        The creation of Som plantation would be executed through S.H.G.s. A total number of 50 S.H.G.s would be formed out of total schematic value 70% would be RSVY fund and 30% would by the born by the beneficiaries for maintenance of the plantation as explained in the remarks column of Table No. 1.

Programme Proposed

A.       ERI SPINNING WITH SUPPLY OF IMPROVED SPINNING CHARKHA

        There is need of providing training to local spinner on modern spinning charkha to upgrade their skill and also to replace the age old primitive practices.

        For this purpose it is proposal to train 900 Nos. women spinner in three years alongwith supply of one No. of improved spinning charkha. An amount of Rs. 84.00 lakhs is proposed for 3 years.

Component wise details of each training programme is as follows :-

1) Duration of training : 1 month

2) Stipend of trainee per month : @ Rs. 60/- per day : Rs.   1,800.00

3) Cost of raw materials per trainee per month ( 10 kg cut cocoon per trainee @ Rs. 200/- per Kg. : 

            Rs.   2,000.00

4) Honorarium to skilled trainer per month per batch of 20 trainee :                                                                                             Rs.   2,000.00

5) Cost of improved spinning charkha (including Tax) : Rs.   5,000.00

6) Miscellaneous cost for arrangement and conduct of training :                                                                                                    Rs.   2,670.00

7) Transportation cost of training materials to training Spot/batch :                                                                                              Rs.   6,000.00

                                                                                                                              

Consolidated action plan of Sericulture activities under R.S.V.Y.

in N. C. Hills District.

                                                                                                                  Table No. 1.

 

Year

Sl.

No.

Activity

Qantity

Total

( Rs.

In Lakh

Remarks

2004-05

(1st Year)

A

1.

 

B

1.

Training :

Eri Spinning Training

 

Plantation :

Creation of Som

plantation

And Nursery

 

300 Nos

 

 

 

 

100 Hac

 

28.00

 

 

 

 

55.13

Since N.C.Hills district is a hilly tract having slope above 8% these proposed Som plantation would be created after terracing.

The cost of terracing as per the Soil Conservation, Assam norms for 2003-04 is Rs. 0.333 lakh per hect. in hilly areas, hence the total expenditure for terracing 200.00 Ha of land would be Rs. 66.60 lakh. This expenditure which is about 30% of the total schematic value would be born by beneficiaries through “Swaram daan”

 

 

Sub Total

 

83.13

2005-06

( 2nd Year )

A

1.

 

B

1.

 

2.

Training :

Eri Spinning Training

 

Plantation :

Creation of Som

Plantation

 

Maintenance of Som Pplantation

 

300 Nos

 

 

100 Hac

 

 

 

100 Hac

 

28.00

 

 

46.00

 

 

 

16.50

 

 

Sub Total

 

90.50

2006-07

( 3rd Year )

A

1.

 

B

1.

Training :

Eri Spinning Training

 

Plantation :

Maintenance of previous years

Plantation.

 

300 Nos

 

 

 

 

200 Hac

 

28.00

 

 

 

 

33.00

 

 

Sub Total

 

61.00

 

 

Grand Total

 

234.63

                                                                                                                                

 

YEAR WISE FINANCIAL INVOLVEMENT

( Spinning & Training )

                                                                                                                    (Rs. in Lakhs)

 

No.

Year

No. of

Trainees

Stipend

Raw

Materials

Honorarium

To skilled

Spinners

Spinning

Charkha

Misc

Expnd

Transportation

Total

1

1st year

300

5.40

6.00

0.30

15.00

0.40

0.90

28.00

2

2nd year

300

5.40

6.00

0.30

15.00

0.40

0.90

28.00

3

3rd year

300

5.40

6.00

0.30

15.00

0.40

0.90

28.00

 

Total

900

16.20

18.00

0.90

45.00

1.20

2.70

84.00

 

IMPACT

        (1)  Around 900 skilled spinners as well as 900 Nos. of modern spinning wheel will be added to the district.

        (2)  900 Nos. of women beneficiaries will be directly benefited by obtaining modern

spinning charkha.

        (3)  Production of Eri silk will be enhanced and spinners will earn more.

        (4)  Eri cocoon growers would find marked to sale their produce with the new spinners added to the market.

        (5)  Create substainable earning avenue among rural B.P.L. family.

            (A) Economic of Eri Spinning on improved charkha ( Per month )

        Assumption :- One skilled spinner can produce about 350 gm of yearn per day with spinning charkha and consume 15 kg. of cut cocoon per month.

        Expenditure :-

                1. Cost of 15 Kg. cut cocoon

                   @ Rs. 200/- per Kg.                          Rs.   3,000.00

                2. Misecellaneous                                        Rs.      100.00

                                                Total :-              Rs.   3,100.00

 

        Out turn :- Spun yarn production - 10 kg. (approx)

        Value of 10 kg. Spun yarn @ Rs. 650/- per kg. Rs.   6,500.00

        Net profit 6,500.00 - 3,100.00 = Rs. 3,400.00 per month/per spinner.

 

 

(B)    Cost benefit ratio of Som plantation in 1.00 Hect. of land.

 

        (1)    Total Nos. of plants     :                               1,100.00

        (2)    DFLS to be reared/plants    :                         2 DFLS

        (3)    Nos. of egg per DFLS :                                 100 Nos.

        (4)    No. of crops / per year   :(in hills)                 3 times

        (5)    Total production of cocoons = 1100x2x100x3

=   6,60,000 Nos. of  

     cocoons.

        (6)    Success rate :                                          50%

=  3,30,000 Nos. of  

     cocoons.

        (7)    Rate of one good cocoons                     :   Rs. 1.00

Total out put                                     =  3,30,000/   

Hect. per year

(8)    Total input                                = 1.173 Lakh/per

Hect.

                (Creation + 2 years maintenance)

        (9)    Cost benefit ratio                               = 1.173 : 3.300

                                                                        = 1 : 2.81

 

IMPACT

        (1)    Around 200 Hect. of barren (Jhumia) land  will be covered by Som plantation.

        (2)    50 Nos. of  Self Help Groups will be directly benefited.

        (3)    It protects the soil and moisture conservation of the topography.

        (4)    Som is an Eco-Economic plantation, which conserve and rejuvenated the Ecological balance.

(5)            Create sub stainable earning avenue among unemployed youths.

  

SOM PLANTATION SECTOR

 

Action plan of Sericulture plantation under R.S.V.Y. in N.C.Hills District.

                                                                                                                                              Table No. 3.

 

Year

Sl.

No.

Activity

Qantity

Total

( Rs.

In Lakh

Total

( Rs. In Lakhs )

2004-05

(1st Year)

1.

 

 

2.

 

 

3.

 

4.

Creation of Som

Plantation

 

Nursery for 200 Hac

Plantation coverage

 

Camp Hut

 

Water tank with accessories

 

100 Hac

 

200 Hac

Coverage

 

5 Nos

 

 

5 Units

 

0.46/Hac

 

 

0.0370/Hac

 

0.260/Unit

 

 

0.086/Unit

 

46.00

 

 

7.40

 

1.30

 

 

0.43

 

 

Sub Total

 

 

55.13

2005-06

( 2nd Year )

1

 

 

2.

 

 

Creation of Som

Plantation

 

Maintenance of Som Pplantation

 

100 Hac

 

 

100 Hac

 

0.46/Hac

 

 

0.165/Hac

 

 

46.00

 

 

16.50

 

 

Sub Total

 

 

62.50

2006-07

( 3rd Year )

1.

Maintenance of Som plantation created during previous years

 

 

200 Nos

 

 

0.165/Hac

 

 

33.00

 

 

Sub Total

 

 

33.00

 

 

Grand Total

 

 

150.63

                                                                                         Table No. 4.

Block wise proposed Som plantation under R.S.V.Y. in N.C.Hills District. 

Sl.

No.

Name of the Block

Area of creation

( Hac )

Remarks

1

Jatinga Valley Dev. Block, Mahur

28.00

 

2

Diyung Valley Dev. Block, Maibang

40.00

 

3

Harangajao ITD Block, Harangajao

50.00

 

4

Diyungbra ITD Block, Diyungmukh

50.00

 

5

New Sangbar Dev. Block, New Sangbar

32.00

 

 

Total

200.00

 

 MODEL SCHEME FOR MUGA CULTURE (SOM PLANTATION)

UNIT = 1.00 Hector.

 

1).    Clearance of Jungle, uprooting of stamps, collection of debris, burning, lay out of land etc. as directed.

        Quantity :-

75 Man days @ Rs. 60/= Man days. ...........................Rs.          4.500.00

2).    Cost of collection of Fencing Materials available locally.

        Quantity :

80 M.D. @ Rs. 60/- M.D. ..........................................Rs.          4,800.00

3).    Erretion of Fencing with locally collect materials.

        Quantity :-

60 Man Days @ Rs. 60/- M.D. ...................................Rs.          3,600.00

4).    Digging of 1125 Nos. of Pits of Size 1’x1’x1’ including transplantation of polytubes seedlings.

        Quantity :-

82 M.D. @ Rs. 60/- M.D. ..........................................Rs.          4,920.00

5).    Cost of transportation of seedlings from Nursery to planting side.

L/S Rs. 4,500/- .....................................................  Rs.          4,500.00

6).    Cost of Vermi Compost required for manuring the plantation

        Quantity :-

L/S 10 quintal @ Rs. 1400/-qntl. ...............................Rs.       14,000.00

 

7).    Cost of Manuring the plantation with vermicompost.

        Quantity :-

85 M.D. @ Rs. 60/- ..................................................Rs.         5,100.00

8).    Weeding and Intercultural operation

        Quantity :-

85 M.D. @ Rs. 60/=                                                 Rs.          5,100.00

9).    Cost of 4 Nos. Spade @ Rs. 145/- each ..........           Rs.             580.00

10).   Cost of 5 Nos. Dao @ Rs. 80/- each ......... .....     Rs.     400.00

                                        Total :-                          Rs. 46,000.00

 

                                        ( Rupees Forty six thousand only )

Therefore cost of raising 1.00 Hector of Som plantation is = Rs. 46,000.00

 

 

Analysis for 2nd and 3rd year Maintenance of Som plantation.

Unit = 1.00 Ha.

 

1).    Cost of gap feeling by Som seedlings @ 10% Mortality

        Quantity :-

1100 Nos. of Seedlings @ Rs. 3/= Seedling. ....................Rs.  3,300.00

2).    Cost of Vermi Compost including its application as per direction.

        Quantity :-

L/S Rs. 5500/-    .........................................................Rs.  5,500.00

3).    Cost of Neem Cakes as antipest.

        Quantity :-

L/S Rs. 2000/- ............................................................. Rs. 2,000.00

4).    Cost of Weeding and intercultural operation.

        Quantity :-

95 M.D. @ Rs. 60/- M.D. ............................................... Rs. 5,700.00

                                                        Total :-              Rs.  16,500.00

 

                               ( Rupees Sixteen thousand and five hundred ) only.

Therefore cost of maintenance of 1.00 Hector of

Som plantation = Rs. 16,500.00

 

 